Cape Town’s iconic Muizenberg beach huts are being temporarily dismantled as the City continues upgrading the popular beachfront.
The City said its contractor would begin removing the four remaining huts on the eastern side of the beachfront.
Four huts on the western side were already removed in March.
All eight will be replaced with new huts designed to be more durable while retaining the historic appearance and layout of the originals.
The beach huts further along the coastline near the river mouth will not be affected and will remain in place.
Historic landmark protected
Muizenberg’s colourful beach huts are among South Africa’s most photographed landmarks.
They are believed to have developed from Victorian-era bathing machines and were formally arranged into a regulated row of 174 wooden structures by the municipality in 1929.
The huts are used by beachgoers, swimmers and surfers as changing spaces or for storing beach equipment.
They have also become a major attraction for tourists, photographers and commercial film crews.
The City said the replacement huts would preserve the beachfront’s heritage and character.
Promenade moving inland
The huts must be relocated because the upgraded promenade will be built about two metres further inland.
According to the City, the setback is needed to respond to rising sea levels and storm surges linked to climate change.
It will also help ensure that the new seawall does not reduce the beach’s width.
The wider refurbishment includes replacing ageing seawalls and upgrading public facilities.
About 60% of the new precast steps and promenade units have already been installed.
Project remains on schedule
Construction began in February 2025 and is expected to be completed by December 2026.
The concrete work for the Surfer’s Corner section of the revetment is nearly finished.
Work has also started on the parking area next to the railway line and on landward landscaping.
Deputy Mayor and Mayoral Committee Member for Spatial Planning and Environment Eddie Andrews said the removal of the remaining huts showed that the project was progressing well.
He thanked local businesses, residents and visitors for their patience during the refurbishment.
The City said work remained on track for completion by the end of the year.